Supporting above-ground main on Dauntless

Summary: Crews began and completed work on March 31.

Current status: This project has been completed.

A crew added support to the above-ground main at Dauntless, where rain had washed a lot of dirt away. Due to this erosion, some parts of the main were left “floating.” This was a preventive action and no customers were out of water due to this project.