Summary: Crews to install 410 feet of new water main on Yacht Harbor Drive.
Current status: Work to begin Sept. 28.
Cal Water is pleased to inform you of an upcoming water infrastructure upgrade project in the Portuguese Bend Beach Club. The project goal is to improve water supply reliability and fire protection in your area.
Scope of Work
The project consists of installing 410 feet of new 8-inch water main pipeline on Yacht Harbor Drive, east of Spindrift Drive.
Timeline
Construction will start September 28, 2026, and is anticipated to be completed by December 18. The work consists of the following activities:
- Exploratory investigations/potholing.
- Construction/installation of above-ground water main pipeline infrastructure.
- Restoration, including paving.
The work will be performed Monday through Friday between 8:30 a.m. and 4:30 p.m. The work will be completed in phases throughout the project to allow for roadway access.
What to Expect
We will make every effort to minimize traffic delays during construction. You can expect traffic control along the roadway and construction noise. “NO PARKING” signs will be placed 48 hours in advance, as required. Please note that Los Angeles County parking requirements are still in effect in construction zones.
Vehicular access to your property will be restricted during construction activities between 8:30 a.m. – 4:30 p.m. until safe access is provided at the end of each day; however, crews will work with you to get in and out of your home.
If any water service interruption is required, we will notify you prior to any planned shutdown. To fulfill water quality requirements, some water flushing may be required. Please be assured that we are committed to conservation and will flush only if necessary.
When completed, all streets, curb, and gutters impacted by the construction will be restored to the existing or better condition. Please be aware that temporary asphalt will be applied until permanent paving is completed approximately 30 days after project completion. This time delay is necessary to allow the trench to become fully compacted, so the road surface is smooth after permanent paving is completed.
Notification
You will receive a notice 48 hours prior to the start of work in front of your property. Site-specific information and contractor contact information will be provided at that time.
We will work hard to minimize any temporary inconvenience to you as we make water system improvements that will benefit our community for years to come. If you have any questions, please contact me at (310) 257-1400.