Harris Reservoir Project Updates
Time-lapse film of construction
August 1, 2011
The Harris Reservoir Project is now complete. If you have any questions, please call us at (805) 497-2757 and we will do our best to address them.



March 11, 2011
- The tank wall — formed and poured in eight separate sections — is now in place, and the wall's steel reinforcement has been stressed. In parallel, tank columns were formed and poured and are also complete.
- The tank's roof was poured on Thursday, March 10 as a single, monolithic pour. In total, 500 yards of concrete was poured, transported by some 60 concrete trucks.
- The next phase of construction will consist of wrapping the concrete reservoir with pre-stressed steel reinforcement, an integral component that will greatly increase the tank's ductility and ability to withstand seismic movement. This is scheduled to be complete by Mid April.
- Overall tank construction is anticipated to be complete by July, barring adverse weather conditions.




August 20, 2010
- Excavation of soil beneath the existing tank and construction of the 25-foot-high temporary wall to support the excavation during the new tank's construction is complete.
- Half of the tank's lower mat concrete foundation has been placed.
- Installation of steel reinforcement continues on the second half. Concrete for this half will be placed in the next few weeks.

April 26, 2010
- Demolition of the existing tanks roof and floor is complete.
- Excavation of the soils beneath the existing tank is underway along with the construction of a temporary wall to support the existing tank walls and the excavation in preparation for new tank construction.
- Over the next 6 weeks or so, the Contractor will continue removing earth from the reservoir and simultaneously constructing the 25' high shored wall that joins the existing reservoir wall.

Older photos

March 2010

January 2010